Jintang Yongqian-104 Gas Recovery Station Completes Initial Trial Run
Update Time:2024-03-20 17:25:36
Views:535

Seizing the momentum for rapid action, Sepmem pushes ahead with project commissioning!

On March 19, 2024, the Yongqian 104 Well Skid-Mounted Natural Gas Recovery Station, part of Chengdu Sepmem Inc.'s Jintang Project, successfully completed its first gas feeding and trial run. On March 20, 2024, the station dispatched its first batch of qualified LNG products, officially entering the production phase.

Construction of the recovery station began on October 16, 2023. Process installation commenced on November 14, and mechanical completion was achieved by January 8, 2024, followed by the "Three Inspections and Four Finalizations" conducted by Chengdu Natural Gas Chemical Plant, which included inspecting design omissions, construction quality, and incomplete work, and finalizing procedures, response measures, operators, and schedules. Under the close collaboration among the Project Department, Engineering Department, Design Department and Technical Management Center, the first batch of qualified products was successfully produced by March 20, 2024.        

As Sepmem's fourth recovery station deployed in Southwest China, its rapid and high-quality completion sets an outstanding example for Sepmem's project delivery. It showcases Sepmem's spirit of efficiency, professionalism, and dedication, and adds luster to the company's stranded gas recovery initiatives.